In a work station for an assembly line, the balance delay is 15%. What is the line efficiency (in %)?
A customer's arrival time is 20 minutes. The service time is 12 minutes. What is the length of the system?
What is the other name for a fixed position layout?
What is the decision-making process to determine when a job is to be started in a machine and when it is to be completed?
For a project activity, the:
to optimistic time = 12 days
tm most likely time = 18 days
te expected completion time = 18 days
What is the variance in days for this activity as per the BETA (β) distribution?
The observed time of operation has been calculated as 15 minutes. The worker was rated at 80% of standard performance. If the relaxation and other allowances were 50% of the normal time, then the standard time could be (in minutes):
The observed time for a particular observation is 1 minute. If the rating factor for that particular operator is 85% and allowances of 25% are to be given, the standard time is (up to 2 decimal places).
A toy company produced 10,000 units and sold them for $10 per unit. 500 labor hours were consumed at a rate of $9 per hour. The total cost of the plastic used in production was $30,000. Given the overhead cost is $15,500, find the total productivity.
If a company has a fixed cost of ₹40,000 and a variable cost of ₹10 per unit for producing circuit breakers, and the selling price is ₹20 per unit, what is the level of production required to achieve a profit of ₹10,000?
A worker X produced 75 units of the same job, while the standard performance is 80 jobs per day. The labor hourly rate is ₹12. (Rate differential to be applied = 80% of the standard piece rate for below-standard performance). For an 8-hour working period in a day, the earnings of the worker will be (in ₹/per day).